Risk register

Describe events, consequences and decisions clearly.

01 / Use the example

See what a useful entry contains

Every row below is illustrative. It shows the level of specificity that makes a record useful: a real event, an accountable role, evidence and a later decision.

02 / Make it yours

Replace before use

Download the editable CSV, delete the example rows, then enter your own case. Check requirements and privacy before adding sensitive details. Review the record with the people doing the work.

Worked example · fictional scenario
Example statusRisk eventConsequenceExisting controlLikelihood 1-5Impact 1-5Owner roleTreatment and due dateReview trigger
ILLUSTRATIVESingle supplier cannot deliverCustomer orders delayedMonthly capacity check34Procurement leadQualify alternate by 2026-11-01Supplier capacity or quality change
ILLUSTRATIVEShared account compromisedClient information exposedMFA and access review25IT leadRemove shared access by 2026-10-15New system or incident
ILLUSTRATIVEKey machine unavailableProduction interruptedWeekly maintenance33Production leadTest spare-part lead time by 2026-10-12Breakdown or increased volume
How to review it

Ask whether an owner can show a dated example, explain the decision and demonstrate that an action changed the result. A completed template alone does not establish conformity with any standard.